Rain delays work cleaning up I-40 rock slide
Crews are hoping they can begin drilling rocks at the top of a massive rock slide on Interstate 40 near the North Carolina-Tennessee state line after rain delayed their progress over the weekend.N.C. Department of Transportation inspector Mike Patton said heavy rains Saturday halted work after the slide area became unstable.
But the Asheville Citizen-Times reported Monday that crews returned the next day to try to move a drill rig they hope to use to test stability near the top of the slide and drill holes for explosives to blow up debris.
The rock slide more than a week ago will keep the interstate closed for at least four months. N.C. Transportation officials say the cleanup could cost $10 million, and Gov. Bev Perdue has declared the slide an emergency.
Tennessee General Assembly
FromRepresentative Vance Dennis
Dated April 4 - April 8, 2011Click here to see Capitol Hill Review.
Dated April 11 - April 15, 2011
Click here to see Capitol Hill Review.
Dated April 18 - April 22, 2011
Click here to see Capitol Hill Review.
Dated May 9 - May 13, 2011
Click here to see Capitol Hill Review.
Final Session Wrap
Click here to see Capitol Hill Review.
Senator Dolores Gresham
Dated March 24, 2011Click here to see Capitol Hill Week from Senator Dolores Gresham.
Dated April 7, 2011
Click here to see Capitol Hill Week from Senator Dolores Gresham.
Dated April 14, 2011
Click here to see Capitol Hill Week from Senator Dolores Gresham.
Dated April 21, 2011
Click here to see Capitol Hill Week from Senator Dolores Gresham.